Hello All,

We agreed to complete Project -“VP Development PH2” For $500, However, you have paid only $200 till date and balance is pending from your side.

We have noticed that you have deducted $100 from agreed amount. The reason for Delay was the following.

1) The timeline assign for the task much less then required development time.
2) Secondly the developer was infected due to covid-19.

Looking at the situation you are Requested to pay the all the due $300 without any delay.

Thanks